Dear Hackney Resident
Works are progressing well on the Kings Hall Leisure Centre project and we wanted to make you aware of some upcoming major demolition works.
We have shown an overall plan below identifying the two areas of demolition:
Orange area (Zone 4)
We are planning to commence the main demolition works to Zone 4 from mid June 2026 up until end August 2026. These works will consist of removal of all internal existing structures down to basement level with use of large machinery. The works may be noisy at times but we will ensure to use noise mitigation measures where we can, which would include use of acoustic screens.
To enable the large machinery to enter the area we will form a ramp from the northern car park, the machine will then sit on a formed platform where demolition will take place from. All demolition material will be distributed to the norther can park prior to be collected from site.
We have shown the approximate location of the ramp below:
Yellow area – Zone 5
The existing concrete slab is in a poor condition and requires full removal and replacement. The existing slab will need to be demolished to the full extent, this will be carried out with hydraulic breaking where feasible which will reduce the noise, dust and vibration. All waste will be distributed to the northern existing car park.
We will ensure to keep the nuisance to a minimum but we do apologise for any inconvenience caused during the works.
Please visit our website for further information, the link can be found below:
https://www.morgansindallconstruction.com/our-projects/live-projects/kings-hall-leisure-centre/
As the Senior Social Value Manager at Morgan Sindall, I will be your dedicated point of contact for all resident liaison throughout the life of the project. If you have any questions or project-related enquiries, please contact me and the project team at:
Email: kingshallleisure@morgansindall.com
If you would like to be added to a project email distribution list, then please drop me a line at the above address, giving your permission to be notified by email of any updates, and confirming your email address.
We are excited to be working in Hackney, and we are committed to ensuring this project creates a positive impact for the borough, bringing opportunities and benefits to local people throughout the duration of the works.
Best wishes,
Monica Paul
Senior Social Value Manager Morgan Sindall Construction - London
Mobile: 07977 354 264