News
|
Ardrossan Project Update (September 2026)
What's been happening?
Over the last four weeks, we've made good progress across the site:
- Continued construction of foundations within the Sports Wing.
- Further construction of the swimming pool floor and walls.
- Installation of additional scaffolding, access platforms, and safety handrails.
- Continued formation of the sports pitches.
- Progress on external wall structures to the Teaching Wing.
- Ongoing roofing works to the Teaching Wing.
- Installation of floor slabs within the Central Wing.
- Commencement of window installation to the Teaching Wing.
What’s coming next over the next 4 weeks?
- Further foundation works within the Sports Wing.
- Additional scaffolding, access, and safety installations.
- Ongoing development of the sports pitches and car park.
- Continued construction of the swimming pool structure.
- Installation of further floor slabs within the Central Wing.
- Continued progress on external walls and roofing to both the Teaching and Central Wings.
- Ongoing window installation to the Teaching Wing.
- Commencement of façade cladding works.
- Erection of structural steel within the Sports Wing.
- Construction of lift shafts.