Over the last four weeks, we've made good progress across the site:
- Finished installing floor slabs in the Central Wing
- Continued foundation works in the Sports Wing
- Made further progress on the new car parks
- Advanced construction of the swimming pool floor and walls
- Installed additional scaffolding, access platforms and safety handrails
- Continued shaping and preparing the outdoor sports pitches
- Progressed external wall construction in the Teaching Wing
- Continued roofing works on the Teaching Wing
- Started installing the building's external cladding
- Begun fitting windows in the Teaching Wing
- Started roofing works on the Central Wing
- Commenced construction of the lift shafts
What’s coming next over the next 4 weeks?
- Continuing foundation works in the Sports Wing
- Further scaffolding and site safety improvements
- Ongoing development of the sports pitches and car parking areas
- Continued construction of the swimming pool structure
- Further progress on external walls and roofing for the Teaching and Central Wings
- Continuing installation of windows in the Teaching Wing
- Ongoing installation of external cladding
- Starting erection of the Sports Wing steel frame
- Continuing work on lift shafts
- Installing filtration pipework for the swimming pool