Skip to content Skip to main menu
October Drone Image

Ardrossan Project Update (October 2026)

News |

Ardrossan Project Update (October 2026)

What's been happening?

Over the last four weeks, we've made good progress across the site:

  • Finished installing floor slabs in the Central Wing
  • Continued foundation works in the Sports Wing
  • Made further progress on the new car parks
  • Advanced construction of the swimming pool floor and walls
  • Installed additional scaffolding, access platforms and safety handrails
  • Continued shaping and preparing the outdoor sports pitches
  • Progressed external wall construction in the Teaching Wing
  • Continued roofing works on the Teaching Wing
  • Started installing the building's external cladding
  • Begun fitting windows in the Teaching Wing
  • Started roofing works on the Central Wing
  • Commenced construction of the lift shafts

What’s coming next over the next 4 weeks?

  • Continuing foundation works in the Sports Wing
  • Further scaffolding and site safety improvements
  • Ongoing development of the sports pitches and car parking areas
  • Continued construction of the swimming pool structure
  • Further progress on external walls and roofing for the Teaching and Central Wings
  • Continuing installation of windows in the Teaching Wing
  • Ongoing installation of external cladding
  • Starting erection of the Sports Wing steel frame
  • Continuing work on lift shafts
  • Installing filtration pipework for the swimming pool
October Drone Image
October Drone Image 2